NEC notice drafting
Draft an NEC notice in minutes, with the clock on screen.
Early warnings, compensation event notifications and other contractual notices for NEC3 and NEC4. Tell us what happened in your own words; we put it in the right paragraphs with the right clause numbers, mark anything you still need to complete and give you a Word file ready to send.
Three steps
- Contract basics. Version, Option, parties. Remembered for next time.
- The notice. Pick the type, describe what happened or fill in a short form.
- Review and send. Letter preview, a checklist of what to complete, download or copy.
Clause numbers come from the drafting code, never from the AI, so a reference cannot be invented.
Examples
What goes in, what comes out.
Three invented scenarios, to show the shape of the notice the tool produces. Your notice uses your facts only.
Early warning: a delivery may slip
A subcontractor tells the site team that the pump sets ordered for the wet well may arrive three weeks late. Nothing has slipped yet, but installation sits close to the critical path.
The tool produces: An early warning notification under clause 15.1 (NEC4) or 16.1 (NEC3), with the matter, why it is notified and a proposed way forward, and a request for an early warning meeting.
Compensation event: late access
Access to the north compound was due on 2 March in the Accepted Programme. The Client gave it on 16 March. The planner notes the date the team became aware and the effect on Key Date 2.
The tool produces: A notification of a compensation event under clause 61.3, with the eight-week clock worked out from the aware date and a marker for the clause 60.1 item if you have not named it.
Other notice: change of key person
The named site agent is moving to another project and a replacement with equivalent experience starts next month. The contract needs the Project Manager told in writing.
The tool produces: A contractual notification with the details, the effect and the action requested, and a reminder to add the clause it is given under and to check for any period it must be given within.
The tool drafts; it does not decide. Whether an event is a compensation event, and which clause 60.1 item applies, is a judgement for you or your adviser. Drafts are aids and do not replace the judgement of a qualified planner or adviser.
Need the programme impact behind the notice?
A compensation event quotation needs a revised programme that shows the effect. CPMP planners build them in P6 and write the narrative that goes with them.