AI programme checker

Know what the Project Manager will question before you submit.

Upload your programme. In about a minute you get the DCMA 14-point assessment and the NEC clause 31.2 content check as a PDF report and a private results page. Every figure is calculated from your file. AI only writes the commentary.

Calculated, not guessed14 DCMA checks and 10 clause 31.2 items, measured by code.
AI writes the notes onlyIt explains the results. It cannot change a number.
About a minutePay, upload, read. No account, no software to install.
Sample reviewXER · DCMA + 31.2
  • FAILLogic
  • FAILNegative float
  • WARNINGLags
  • PASSCritical path test

From a synthetic, deliberately flawed programme. Your results come from your file.

Not sure yet? Run the free health check on your XER first: counts and your three biggest issues in seconds, nothing stored.

Choose your review

One-off fee. No subscription, no account.

Pick the file you have. The XER review is the full assessment; the PDF review checks the content only, because a PDF carries no schedule data.

PDF review

£29 one-off

For a programme printed to PDF from any planning tool.

  • The 10 NEC clause 31.2 content items
  • Starting date, access dates, Key Dates, Completion Date, planned Completion
  • Float, time risk allowances, critical path
  • Work of the Client and Others; acceptances, information and access you need
  • Plain-English commentary and what to do first
  • PDF report and a private results page

A PDF holds no schedule data, so there is no DCMA analysis. The check looks for each item in the printed content.

Card payment by Stripe. Your card details never touch our servers.

  1. Step 1

    Pay

    Card payment through Stripe. Your card details never touch our servers.

  2. Step 2

    Upload

    Drop your file on the page we take you to. You watch each stage run.

  3. Step 3

    Read and download

    Results on screen in about a minute, with the PDF report to download and a private link to share.

Sample results

Run on a synthetic, deliberately flawed XER.

What you get

A report you can hand to the Project Manager, or to your planner.

The online results page and the PDF say the same thing. Both open with the counts and the summary, then list every check with its result, the threshold it was judged against and example activities.

  • Score strip: passes, warnings, fails and items that could not be assessed.
  • Summary and what to do first: three to five actions, most important first.
  • Every check, one by one: result, threshold, plain-English note and the activity codes behind it.
  • A private link that you can share with your team. No account, no login.

What is checked

The 14 DCMA checks and the 10 clause 31.2 items.

Thresholds are the ones the tool applies. Percentage checks pass at or under the limit, warn up to twice the limit and fail above that. Index checks pass at 0.95 and warn from 0.85.

DCMA 14-point assessment (XER review)

No.CheckWhat is measuredPassWarningNot assessed when
01LogicIncomplete activities with no predecessor or no successor≤ 5%Over 5% up to 10%Always assessed
02LeadsRelationships with a negative lag0%None: any lead failsAlways assessed
03LagsRelationships with a positive lag≤ 5%Over 5% up to 10%Always assessed
04Relationship typesShare of relationships that are finish-to-start≥ 90%80% up to 90%No relationships in the file
05Hard constraintsIncomplete activities with a mandatory or "on or before" constraint≤ 5%Over 5% up to 10%Always assessed
06High floatIncomplete activities with total float over 44 working days≤ 5%Over 5% up to 10%Always assessed
07Negative floatIncomplete activities with negative total float0%None: any negative float failsAlways assessed
08High durationIncomplete activities with an original duration over 44 working days≤ 5%Over 5% up to 10%Always assessed
09Invalid datesForecast dates before the data date, or actual dates after it0None: any invalid date failsNo data date in the file
10ResourcesActivities with duration but no resources assignedInformation onlyNot scoredProgramme not resource-loaded
11Missed tasksActivities due to finish by the data date per baseline that finished late or are still open≤ 5%Over 5% up to 10%No baseline (target) dates
12Critical path testA continuous chain of critical activities links the start of the remaining work to the project finishContinuous pathNone: a broken path failsNo float data
13Critical Path Length IndexCritical path length plus project total float, divided by critical path length≥ 0.950.85 up to 0.95No data date or float data
14Baseline Execution IndexActivities completed divided by activities baselined to be complete by the data date≥ 0.950.85 up to 0.95No baseline (target) dates

NEC clause 31.2 content check (both reviews)

Each item is evidence-based. The check reports whether the item can be found in the programme (activity names, milestones, dates and float in an XER; the printed content of a PDF). It cannot judge whether the content is right, only whether it is there.

No.ItemWhat the programme must showPass
01Starting dateThe starting date is shown.Shown in the programme
02Access datesThe dates on which the Contractor is given access to each part of the Working Areas are shown.Shown in the programme
03Key DatesEach Key Date is shown, with the date the Contractor plans to meet it.Shown in the programme
04Completion DateThe Completion Date for the whole of the works is shown.Shown in the programme
05Planned CompletionPlanned Completion is shown, so it can be compared to the Completion Date.Shown in the programme
06FloatProvisions for float are identified.Shown in the programme
07Time risk allowancesTime risk allowances are identified and set out.Shown in the programme
08Critical pathThe critical path can be identified.Shown in the programme
09Work of the Client and OthersThe order and timing of the work of the Client and Others is shown.Shown in the programme
10Acceptances, information and access neededThe dates by which the Contractor needs acceptances, information and access are shown.Shown in the programme

PDF or XER

What each review includes.

IncludedPDF review, £29XER review, £79
File you uploadPDF printed from your planning toolPrimavera P6 XER export
NEC clause 31.2 content check (10 items)Yes, from the printed textYes, from activities, milestones and dates
DCMA 14-point assessmentNo schedule data in a PDFAll 14 checks
Critical path continuity testText mention onlyCalculated from the logic
Project name and data date read from the fileNot availableYes
Offending activity codes listedText snippets insteadUp to 25 per check, 6 shown in the report
Plain-English commentary and what to do firstYesYes
PDF report and private results pageYesYes
A planner on the end of the formYesYes

Before you pay

Straight answers on your file, your money and the limits of the tool.

How your file is handled

  • Stored privately and used only to produce your review.
  • Never shared. Never sent to the AI: the AI sees the calculated results, not the file.
  • Your results sit at a private link. Anyone you send it to can read them; nobody else can.
  • The detail is in our privacy and terms.

Payment and your money

  • Payment is taken by Stripe on their checkout page. Your card details never touch our servers.
  • One-off fee. Nothing recurring, nothing to cancel.
  • If we cannot read your file your money is safe: the page gives you a reference, you email us quoting it, and we put it right.

What the tool does not do

  • It does not predict whether the Project Manager will accept the programme. It shows what they are likely to question.
  • It does not judge whether your content is right, only whether it is there and whether the schedule mechanics meet the thresholds.
  • It does not replace a planner. Fixing logic, rebuilding a critical path and writing the narrative is still a person's job.
  • If the file is out of date, so are the results.

Why we built it

These are the checks our planners run by hand before any programme goes to a Project Manager. Most refusals we see come down to the same handful of things: broken logic, negative float, missing time risk allowances, no clear critical path. Putting the checks in a tool means a contractor can see the problems in a minute rather than hearing about them in a rejection.
The CPMP directors

Meet the team

Questions

Frequently asked.

Which file types can I upload?

A Primavera P6 XER file for the full review, or a PDF printed from your planning software for the clause 31.2 content check. The PDF must contain real text: a scanned image cannot be read. Files up to 40 MB.

How do I export an XER from P6?

In Primavera P6 open the project, then choose File, Export, Primavera PM (XER), select the project and save the file. Export one project per file so the checks run on that programme alone.

Do you take Microsoft Project (MPP) files?

Not yet. MPP support and month-by-month tracking are coming with accounts. For now, PDF is the route for Microsoft Project, Asta and other tools.

Does the review use my baseline?

For an XER, yes where the file holds target (baseline) dates: the missed tasks check and the Baseline Execution Index use them. If the file holds no target dates, those two checks are reported as not assessed rather than guessed.

What if my programme has no resources?

Nothing else changes. The resources check is information only and is reported as not assessed when the programme is not resource-loaded. The other 13 checks and the clause 31.2 items run as normal.

What is the data date and why does it matter?

The data date is the date the programme was last updated to, read from your file. Invalid dates, missed tasks, the Critical Path Length Index and the Baseline Execution Index are all measured against it. If the file has no data date those checks are shown as not assessed.

How is AI used?

Only to write the commentary. Every figure, status and list of activities is calculated by code from your file and is final before the AI sees it. The AI receives the calculated results, not your file, and is told it may not add, round or estimate numbers. If the AI is unavailable, a plain template writes the notes instead.

What happens if you cannot read my file?

Your money is safe. The results page tells you what went wrong and gives you a reference. Email us quoting that reference and we will put it right.

Who sees my data?

Your file is stored privately and used only to produce your review. It is not shared and it is not sent to the AI. Your results live at a private link that only you have. See our privacy and terms page for the detail.

Can CPMP fix what the review finds?

Yes. Every results page has a short form that goes straight to a CPMP planner with your reference attached. We can repair the logic, rebuild the critical path, write the clause 31 narrative and keep the programme accepted month by month.

Something else? Email hello@cpmp.co.uk or call 01403 888 342, Monday to Friday, 9am to 5pm.

Ready when your export is.

Pay, upload, read. About a minute from file to report, with a planner one form away if you want the problems fixed.

AI programme checker for NEC: DCMA 14 and clause 31.2 | CPMP