NEC for beginners: who does what and how a problem is handled

A plain walk-through of the NEC roles and the first weeks of a job, with an invented culvert problem followed from discovery to payment.

NEC basics for newcomers3 min read

On this page
  1. Who is who
  2. The first weeks
  3. One problem, start to finish
  4. Five habits worth learning first
  5. What newcomers get wrong
  6. Related guides

Here is NEC in one sentence: you agree the deal, then follow set procedures to warn each other, price change and keep the programme current until the job is done. The procedures are the part to learn first, because the contract expects them to be part of the daily routine. This guide uses the NEC4 Engineering and Construction Contract (ECC). NEC3 has the same ideas under some different names and numbers.

Who is who

Role What they do for you to know
Client Pays, and supplies what it promised, such as access to site
Contractor Builds to the Scope (the description of the work and any constraints), and produces the programme and quotations
Project Manager Acts for the Client: gives instructions, deals with compensation events, assesses payment
Supervisor Checks quality: tests, inspections, notifying Defects
Subcontractors Work for the Contractor, often on their own NEC subcontract

The first weeks

  1. Find your Contract Data. It holds the dates, periods, Options and rates for your job. Keep a copy beside you.
  2. Get a programme in. If the Contract Data names none, the Contractor must submit one for acceptance within the period stated. Fail, and the Project Manager holds back a quarter of the value of work done at each assessment until you do (50.5).
  3. Open the Early Warning Register. It lists matters that could affect cost, time or quality. The first meeting about it follows soon after the starting date.
  4. Start the routine. Assessments, programme revisions and warning meetings repeat from here on.

One problem, start to finish

Imagine a school extension on Option A, with round figures. In week 9 the groundworkers uncover an old brick culvert that no drawing shows. One foundation must change.

  1. Same day: the site manager tells the commercial team, who give the Project Manager an early warning (15.1) and log it.
  2. That week: a meeting compares options. Bridging over the culvert is cheaper than diverting it, so they bridge.
  3. Instruction: the Project Manager changes the Scope. That is a compensation event (60.1(1)), and it asks for a quotation.
  4. Within three weeks: the Contractor prices the extra Defined Cost (the actual cost of the work, as defined by the contract) and the Fee, say £22,000, and shows planned Completion moving five days (62.2, 62.3).
  5. Within two weeks: the Project Manager checks the numbers and accepts.
  6. Implementation: the Prices rise by £22,000, the Completion Date moves five days, and the next programme shows it (66.1).

Many contract forms would leave this to be argued months later. NEC aims to settle it in a few weeks, while everyone remembers what happened.

Five habits worth learning first

  • Read your own contract, including Z clauses that may alter what you have been taught.
  • Know the key period. You have eight weeks from becoming aware of a compensation event to notify it, with limited exceptions (61.3).
  • Write things down. A communication must be in a form that can be read, copied and recorded (13.1). A chat on site does not count.
  • Use the right person. Instructions come from the Project Manager. Defects come from the Supervisor. A request from anyone else may not be an instruction.
  • Look forward. Early warnings and quotations deal with what will probably happen, not only what already has.

What newcomers get wrong

Many assume an early warning admits fault or starts a claim. It does neither. It tells the other side there is a problem while something can still be done. Another trap is treating the Accepted Programme as wall decoration: delay is measured against it, so an out-of-date one means being judged from the wrong starting point.

This guide is general information, not legal advice. Check it against your contract.

Was this useful?